Point of Sale (POS) Printer Rollout Study For Grocery Stores

If your company has experienced complications andover 1,540 sites, the National Contractor selected two
hardship trying to roll out new technologies to severalexperienced Project Managers (PMs) to supervise the
locations across the country, you may benefit fromjob from start to finish. Once the scope of work was
this article. As you would likely agree, communicationestablished, the Project Managers searched in its large
and constant attention to detail are vital aspects to adatabase for qualified technicians near each location
successful roll-out. Problems can arise at any momentwho were experienced in infrastructure cabling
during a nationwide roll-out with obstacles at eachinstallation for similar marketplace buildings. The National
unique location and difficulty coordinating each step ofContractor also calculated optimum driving routes for
the process.the techs to minimize travel time and be more
A Global Provider specializing in "customer drivencost-efficient with the installations.
marketing" for international grocery, drug and massAnother challenge with this point of sales printer
merchandiser stores, was in need of an organized andproject was that the Customer did not want the
meticulous management team to complete a projectstores or its customers to be affected by the cabling
requiring service at over 1,500 different site locations.installation. Thus, the Project Managers confirmed with
This Provider/Customer distributes printed couponthe selected technicians that they were willing to work
advertisements at point-of-sale checkout counters inafter-hours to do the job to maintain activity in the
over 23,000 grocery, mass merchandise, andstores. The National Contractor was able to
pharmacy stores nationwide. The Customer wasaccommodate the after-hours request, and
looking to upgrade their point of sale hardware incorresponded with the Customer's on-site
various stores from black & white to high-speed pointrepresentatives to ensure access to the stores at
of sale color printers.night. The store managers also had input in this planning
The job required installation of upgraded infrastructureand The National Contractor adjusted its time schedule
cabling in over 8,000 lanes at stores owned by 11 largearound the busier days for the store such as blackout
supermarket chains. The Customer needed to ensuredates (i.e. double coupon promotions). This flexibility of
that the new data cabling, which would accommodatework hours made it convenient for the Customer to
incoming point of sale color printers, was properlyupgrade its systems while the stores remained open.
installed and functional before distributing the newA common cause for costly delays at the beginning of
printers to the respective locations. The project wasa large rollout is the absence of supplies that the
expected to be costly and complicated because oftechnicians need to install the cables. To avoid this
the vast number of unique locations.problem, The National Contractor's PMs ordered bulk
Multiple challenges were identified for the customer inmaterials to help save the Customer money and
this case, but with no clear way to solve themfollowed a strict schedule to have all necessary
simultaneously.installation materials available before the techs arrived
1. Customer needed custom cabling designs for multipleat the locations. While some companies suffer from
locations due to the different layouts of the stores.the confusion of task scheduling with multiple sites, this
2. Customer needed a way to coordinate andNational Contractor uses its signature management
organize the on-going activity and installation at eachtool, Advantage®, to monitor and update the activity
individual site.occurring at each site on a daily basis. Using the
3. Customer needed to find contractors at eachAdvantage® System, the PMs were able to keep
location who were qualified to complete the installation,track of where installations were occurring every
without detracting from the quality of service providedsingle day.
by each contractor.During the installation, the Customer did not want the
4. Customer had to ensure that the cabling installationsin-place coupon printers to be inactive so The National
would not cause the stores to close for installation norContractor devised a plan where the technicians
would it be bothersome to the shoppers.installed the new cables before removing the old ones.
5. Customer had to verify that the work wasThus, the printers were always online and operating
completed in a timely and high-quality fashion with theduring the installation period, until the new cables were
system being fully ready for implementation with theinstalled and ready for use. This type of quality
new printers.assurance demonstrates this National Contractor's
With all of these evident challenges to the job, thisability to customize its plans to the requests of the
Global Provider chose to enlist A National Projectcustomer on any given job.
Management and Cabling Contractor to complete theThe Customer's initial apprehension about the quality of
multifaceted project.work was put to rest when The National Contractor
After receiving the contract from the Customer, theexplained the steps that each technician would take
National Contractor initiated its standard procedures, aswith the installation. Upon arrival, the selected tech
follows:would administer a "Pre-Installation Survey" to verify
1. Identified the scope of work.that all the printers were up and functioning properly.
2. Met with the customer to discuss the criteria of theThen, the tech would confirm with the Project
job and the specifications of the installationsManager which installation option to use at the site and
3. Visited a pilot site location to obtain a visualinstall the new CAT5 data cables from the lanes to
understanding of the project.the Communications Room. For a typical contractor,
4. Met with a subcontractor who was familiar with thethis would be considered a completed job and the
typical grocery store layouts to gain an outsidetechnician would leave, sometimes without notice,
perspective on the best pathways to use for theassuming that everything was working fine. This
cabling.National Contractor, insists on active communication
Following this diagnostic process, the Internal Teambetween the Customer, technician, and Project
collaborated to establish two viable options for theManager to assure the techs sign-in and sign-out with
cabling installation, to overcome the issue of variousthe store manager each day on site.
store layouts at the site locations. This solves the firstAs the customer, it can be very frustrating and often
challenge mentioned above because the Nationalcostly for an installation to be completed without
Contractor produced custom designed methods forchecking to make sure everything is working as
the cabling to be installed.expected. The National Contractor's quality assurance
The actual work to be completed was the removal ofprogram includes that technicians at every store
old cabling from the stores' infrastructure and theconduct a "Post-Installation Survey" where the new
installation of new CAT5 data cables at eachCAT5 cables were connected to the current printers
checkout lane in every store. The National Contractorand tested to make sure it was working. The
produced two options for the installation depending onCustomer's plan was to install the new point of sale
the layout of the store. If the pathway allowed for it,color printers after the cabling was completed and The
the "Homerun" option consisted of running cables fromNational Contractor made this much easier by
each of the lanes directly to the Communicationsproviding cabling that was tested and functional, so that
Room. If there were space limitations in the pathway, athe new printers simply needed to be shipped to the
second solution was created in which the cableslocations and plugged in.
would be condensed at a midpoint and then two newThe new printers rollout consisting of 1,540 store
backbone cables (a primary and a backup) would beinstallations for the Global Provider was completed in
run to the Communications Room. One of these twoapproximately nine months, within the estimated time
options would be suitable for every location and Theframe. All challenges identified by the Customer,
National Contractor began checking the floor plans ofincluding quality assurance of installation and supervision
each site to determine which option should be used.with each store location, were completed in an
As mentioned previously, some of the concerns aboutorganized and efficient effort by The National
executing a multi-site technical roll-out are theContractor team. Accomplishing a project of this
uncertainty about the quality of work that you willmagnitude can often be costly and complicated which
receive from each individual technician and whether oris why The National Contractor can benefit companies
not they are qualified to do the job. Without any priorby providing ease of mind that the desired outcome
experience, you never know exactly what kind ofwill be achieved in a methodical and cost-effective
service you will get from the various contractors. Thus,way. For this Global Provider, The National Contractor
an established National Contractor has an in-depthwas able to offer a more competitive price by
procedure for selecting and qualifying technicians assupplying bulk materials at a lower average cost and
well as a comprehensive process to ensure that yourwith a more efficient Management Team. The decision
installation is performed in a professional andprocess for selecting a suitable, yet competent
customer-friendly manner.contractor can be hectic and time-consuming. The
Labeling oneself as professional is one of the mostNational Contractor team strived to make the entire
typical ways a company can project an image ofduration of a project as painless as possible for the
qualification. As the customer, you don't want toCustomer with the belief that through efficient
discover after-the-fact that the contractor you hired ismanagement and by utilizing the right tools, any job can
not only careless, but difficult to work with. With thisaccomplished at a superior level.
Global Provider facing a project with coordination of